McGhee Tyson Airport · Flight Plan
The TYS expansion, step by step.
A garage, a thirteenth gate, a bigger checkpoint, then six more gates and a larger terminal. Here is every Flight Plan milestone from 2024 to 2035, each with its source.
Photo: Jackmcafee, CC BY-SA 3.0 / Wikimedia Commons
Short answer
Flight Plan is McGhee Tyson's decade-long expansion, launched Nov 7, 2024. A $186 million garage with 3,500 more spaces is due in summer 2027. Gate 13 was added in fall 2026. A $10 million checkpoint expansion was set to start construction in fall 2026. The airport's terminal plan adds six gates by about 2030 and bigger ticketing, baggage and security areas by about 2035.
Verified Oct 19, 2026
Knox Nonstop is an independent guide, not the airport. For live parking, flight status and official notices, use flyknoxville.com.
At a glance
Flight Plan in four numbers
Interactive
Every milestone, sourced.
Filter by what is done, what is under way and what is planned. Each entry links to where we confirmed it.
Flight Plan launches; garage breaks groundDone
The airport authority broke ground on the Parking Garage Expansion and Terminal Roadway Improvement Project and announced Flight Plan, a decade-long growth plan. The garage: $186 million, six stories, 3,500 more spaces.
Source: McGhee Tyson Airport: Introducing Flight Plan (Nov 7, 2024)
East and West ramps expandedDone
More aircraft parking space on the airfield, which the airport says positions TYS for new service and smoother turnarounds.
Source: McGhee Tyson Airport: East and West ramp expansion complete (Aug 1, 2025)
The garage goes verticalDone
Tower cranes arrived for the vertical construction phase of the new garage.
Source: McGhee Tyson Airport: Parking garage construction is going vertical (Oct 21, 2025)
Terminal expansion enters environmental reviewDone
The airport published the Environmental Assessment for its Terminal Area Development Program, the federal review the FAA leads before a project like this can proceed.
Source: McGhee Tyson Airport: Environmental Assessment, Terminal Area Development Program (Dec 5, 2025)
New escalatorsDone
Replacement escalators opened. The old set had run since 2001 and carried more than 25 million passengers.
Source: McGhee Tyson Airport: Escalators are back in service (Dec 17, 2025)
Public meeting on the terminal planDone
Community members met the project team to ask questions and comment on the Environmental Assessment.
Source: McGhee Tyson Airport: Public meeting held on the Environmental Assessment (Jan 14, 2026)
New concourse furnitureDone
Lounge seating, work tables and cyber bars with power raised concourse seating capacity by more than 65%.
Source: McGhee Tyson Airport: New concourse furniture (Apr 20, 2026)
$10 million for the checkpointDone
TYS was selected for $10 million from the final round of the FY2026 IIJA Airport Terminal Program to expand the security checkpoint.
Source: McGhee Tyson Airport: TYS receives $10 million for security checkpoint expansion (Jun 3, 2026)
Gate 13 and the renumberingDone
A thirteenth gate was added and gates 7 to 13 were renumbered in three weekly phases. Gate 13 was in use on the airport's live board by Oct 19, 2026.
Source: McGhee Tyson Airport: A new gate coming to TYS (Sep 21, 2026)
Garage canopy and the lower-level laneUnder way
The left lower-level lane closest to the garage is closed while crews build a covered walkway from the new garage to the terminal.
Source: McGhee Tyson Airport: Temporary lane closure, lower level (Aug 24, 2026)
Checkpoint construction beginsUnder way
The airport said in June 2026 that construction on the checkpoint project would begin this fall, after design work.
Source: McGhee Tyson Airport: Seen at TYS this summer (Jun 1, 2026)
The new garage opensPlanned
The airport says the garage project will be completed in summer 2027: six levels, 3,500 more spaces and one floor for rental car operations.
Source: McGhee Tyson Airport: Seen at TYS this summer (Jun 1, 2026)
4.1 million passengers forecastPlanned
The Environmental Assessment projects 4.1 million passengers by 2027.
Source: McGhee Tyson Airport: Environmental Assessment, Terminal Area Development Program (Dec 5, 2025)
Bigger checkpoint finishedPlanned
WVLT reported that the checkpoint expansion is likely to be completed in 2028.
Source: WVLT: McGhee Tyson receives $10 million grant to expand security checkpoint (Jun 9, 2026)
Phase 1: six more gatesPlanned
Expand the Y concourse by six gates, rebuild about 96,000 square yards of terminal apron, repurpose ground transportation Lot F, and relocate the glycol tank farm, deicer storage and the Hertz maintenance building. Forecast: 4.7 million passengers by 2030.
Source: McGhee Tyson Airport: Environmental Assessment, Terminal Area Development Program (Dec 5, 2025)
Phase 2: a bigger terminalPlanned
Expand ticketing, baggage handling and the security checkpoint area, improve utilities, and relocate part of Taxiway A. Both phases depend on funding.
Source: McGhee Tyson Airport: Environmental Assessment, Terminal Area Development Program (Dec 5, 2025)
Showing all 16 milestones.
Growth
Why TYS needs it
The airport says the terminal was built for about 2.6 million passengers a year. Traffic passed that in 2024. The Environmental Assessment also cites airlines switching from regional jets to larger narrow-body aircraft and aging infrastructure.
Components
The seven Flight Plan projects
Garage and terminal roadway
The first project: the $186 million garage and roadway improvements, under way since Nov 2024.
Concourse seating
New furniture in April 2026 raised concourse seating by more than 65%.
Concourse gates
Gate 13 in fall 2026; six more gates in the Phase 1 plan.
Security checkpoint
$10 million federal grant in June 2026; construction from fall 2026.
Ticket counters
Ticketing expansion is part of the Phase 2 plan, estimated for 2035.
Escalators
Replaced; back in service Dec 17, 2025.
Concessions
More concessions and restrooms are on the airport's "What's Next" list.
The seven components as listed on the airport's Flight Plan page (updated May 1, 2026). The Knoxville News Sentinel put the whole program at about $700 million over the decade (Dec 6, 2024); the airport links that story from its Flight Plan page, but has not published its own total.
Process
How the terminal plan gets approved
Environmental Assessment
Under the National Environmental Policy Act the FAA is the lead federal agency. It reviews the airport's assessment and issues an environmental finding on the proposed terminal work.
Have your say
The airport takes questions and comments on the assessment at comments@tys-ea.com and says it will post meeting notices and materials on its project page.

In the meantime
Parking is tight until 2027.
Check the rates, the lane closure and the cheapest lot for your trip.
Photo: Pexels
More airport guides
Questions
What is McGhee Tyson Airport's Flight Plan?
When will the new parking garage at TYS be finished?
Is McGhee Tyson Airport adding gates?
Why is the Knoxville airport expanding?
How much does Flight Plan cost?
When will the TYS security checkpoint expansion be done?
Sources
- McGhee Tyson Airport: Introducing Flight Plan (Nov 7, 2024)
- McGhee Tyson Airport: Flight Plan program page (updated May 1, 2026)
- McGhee Tyson Airport: Seen at TYS this summer (Jun 1, 2026)
- McGhee Tyson Airport: East and West ramp expansion complete (Aug 1, 2025)
- McGhee Tyson Airport: Parking garage construction is going vertical (Oct 21, 2025)
- McGhee Tyson Airport: Environmental Assessment, Terminal Area Development Program (Dec 5, 2025)
- McGhee Tyson Airport: Escalators are back in service (Dec 17, 2025)
- McGhee Tyson Airport: Public meeting held on the Environmental Assessment (Jan 14, 2026)
- McGhee Tyson Airport: New concourse furniture (Apr 20, 2026)
- McGhee Tyson Airport: TYS receives $10 million for security checkpoint expansion (Jun 3, 2026)
- WVLT: McGhee Tyson receives $10 million grant to expand security checkpoint (Jun 9, 2026)
- McGhee Tyson Airport: A new gate coming to TYS (Sep 21, 2026)
- McGhee Tyson Airport: Departures & Arrivals live board (gates read the night of Oct 19, 2026)
- McGhee Tyson Airport: Temporary lane closure, lower level (Aug 24, 2026)
- McGhee Tyson Airport: Reflecting on a record year for air service (Mar 9, 2026)
- McGhee Tyson Airport: TYS serves 3.3M passengers in 2024 (Jan 27, 2025)
- McGhee Tyson Airport: 2019 marks busiest year (Feb 5, 2020)
- McGhee Tyson Airport: Record-breaking year in 2017 (Jan 31, 2018)